D-Day Museum Car Park, Portsmouth

MEC Piling fully designed and successfully installed a contiguous piled retaining wall made up of 145 No. 350mm diameter CFA piles. The job was completed for MEC Groundworks as part of the full piling and piling attendance package they are completing for their client. The piles were required to retain the existing listed wall during the construction process of a new D-Day Memorial.


By working closely with the main Groundworks team, we as the MEC Group completed the works successfully to a high standard of quality and safety. The two main items of plant used on the historic site were our GEAX EK 60L CFA piling rig to bore the piles and a 13T excavator to be in full time attendance.